PeopleSoft Project News - July 27, 2009

Admissions has two additional tasks on their to-do list this week. They have one week to complete their security definitions and they must brief the ITS Helpdesk on possible on-line application for admission issues to they can prepare to answer questions from applicants.

Large scale testing took place for the bio/demo conversion data. This involved the entire project team.

Rory Weaver, the Project Manager, will be in Kearney on Wednesday, July 29, to provide a status update to the Administrative Council and administrative directors.