The StarRez team, including representatives from Residential & Greek Life, ITS, Student Accounts, Student Records and Admissions, have been meeting regularly with StarRez, the CCI consultant, and the Nebraska State College campus representatives to plan the interfaces between StarRez and PeopleSoft Campus Solutions.
Testing of Bundle 15 is nearing the finish.
Premier, the group hired to assist with conversion of data to PeopleSoft, is working with transfer data through Friday, December 18.
Student Records, Student Financials and Financial Aid continue their deployment efforts.
Admissions is utilizing a re-designed New User Registration Form that should be easier for applicants to navigate.
Wednesday, December 16, 2009
Tuesday, November 10, 2009
PeopleSoft Project news - November 10, 2009
Undergraduate Admissions, Graduate Admissions, and International Admissions are admitted students into PeopleSoft for the Fall, 2010, term.
Undergraduate Admissions, with help from the ITS technical staff, is working on the interface between PeopleSoft and EMAS.
Financial Aid is using PeopleSoft to work with the students newly admitted for Fall,2010.
Student Records is building the Fall, 2010, class schedule in PeopleSoft.
Student Records, with help from the ITS technical staff, is converting “cpp” data, which stands for career-program-plan and identifies academic programs/majors.
An interface with SAP is scheduled for testing.
Undergraduate Admissions, with help from the ITS technical staff, is working on the interface between PeopleSoft and EMAS.
Financial Aid is using PeopleSoft to work with the students newly admitted for Fall,2010.
Student Records is building the Fall, 2010, class schedule in PeopleSoft.
Student Records, with help from the ITS technical staff, is converting “cpp” data, which stands for career-program-plan and identifies academic programs/majors.
An interface with SAP is scheduled for testing.
Tuesday, November 3, 2009
PeopleSoft Project News - November 3, 2009
Admissions is attempting to follow up with applicants who have completed or partially completed the online admissions application but have not submitted the application.
Everyone is awaiting the installation in production of Bundle 14, a set of updates to PeopleSoft Campus Solutions, so that review of Bundle 15 can begin.
Everyone is awaiting the installation in production of Bundle 14, a set of updates to PeopleSoft Campus Solutions, so that review of Bundle 15 can begin.
Tuesday, October 20, 2009
PeopleSoft Project News - October 20, 2009
Admissions is working on redesigning the application process so there is consistency among the five applications that talk to each other while the applicant enters the required information.
Financial Aid is reviewing security roles for access to data.
Conversion of data continues.
Updates to PeopleSoft caused issues for the Resource 25 implementation.
The StarRez go-live date was moved from February 2, 2010 to February 15, 2010.
Financial Aid is reviewing security roles for access to data.
Conversion of data continues.
Updates to PeopleSoft caused issues for the Resource 25 implementation.
The StarRez go-live date was moved from February 2, 2010 to February 15, 2010.
Wednesday, October 7, 2009
PeopleSoft Project News - October 6, 2009
Undergraduate and Graduate Admissions are live, accepting applications for admission for Fall, 2010, via the new online application process and PeopleSoft.
Graduate Admissions developed a document imaging and workflow application to integrate with their application process. That, too, is live.
Financial Aid has live functionality for Fall 2010 scholarships. (The Financial Aid go-live process will be a phased-in approach.)
Student Financials and Student Records are working on their implementations. Student Records has critical dates for creating a class schedule and converting data, with registration for Fall, 2010, scheduled in March, 2010. Student Financials plans to go live in May, 2010.
Implementation of DegreeWorks, the new degree audit system, will begin in January, 2010.
Implementation of R25 for classroom scheduling is in progress.
StarRez, a housing software package, is on target for a February, 2010, go-live date.
Graduate Admissions developed a document imaging and workflow application to integrate with their application process. That, too, is live.
Financial Aid has live functionality for Fall 2010 scholarships. (The Financial Aid go-live process will be a phased-in approach.)
Student Financials and Student Records are working on their implementations. Student Records has critical dates for creating a class schedule and converting data, with registration for Fall, 2010, scheduled in March, 2010. Student Financials plans to go live in May, 2010.
Implementation of DegreeWorks, the new degree audit system, will begin in January, 2010.
Implementation of R25 for classroom scheduling is in progress.
StarRez, a housing software package, is on target for a February, 2010, go-live date.
Tuesday, September 29, 2009
PeopleSoft Project News - September 29, 2009
Admissions has discovered two major problems. There is a 30-45 minute delay in establishing a role for a new applicant. This is not an acceptable time frame for completing an application. Also, there are times when the application process does not communicate correctly with our payment software. Both issues are under review.
Financial Aid is planning to go live with limited functionality within a week.
Data conversion and portal development continue.
Financial Aid is planning to go live with limited functionality within a week.
Data conversion and portal development continue.
Tuesday, September 22, 2009
PeopleSoft Project News - September 22, 2009
Undergraduate Admissions and International Admissions are live but working on issues related to PeopleSoft and to EMAS.
Graduate Admissions is learning from the experiences of Undergraduate Admissions and planning to go live as originally scheduled on October 1.
Financial Aid is addressing issues related to reporting for their upcoming go live date.
Student Records has fourteen conversions as well as numerous other procedures to test.
Portal development continues, changing the focus from the needs of applicants to the needs of currently enrolled students.
Graduate Admissions is learning from the experiences of Undergraduate Admissions and planning to go live as originally scheduled on October 1.
Financial Aid is addressing issues related to reporting for their upcoming go live date.
Student Records has fourteen conversions as well as numerous other procedures to test.
Portal development continues, changing the focus from the needs of applicants to the needs of currently enrolled students.
Tuesday, September 15, 2009
Undergraduate Admissions Is Live - September 15, 2009
Undergraduate Admissions is live on PeopleSoft today!
Monday, September 14, 2009
PeopleSoft Project News - September 14, 2009
The PeopleSoft Implementation team had a difficult weekend and due to issues beyond the control of the UNK campus, Undergraduate Admissions did not go live today as scheduled.
Tuesday, September 1, 2009
PeopleSoft Project News - August 31, 2009
Undergraduate Admissions is planning the roll out of the online application for admission for Fall 2010 applicants on September 14.
The MyBlue Portal will go live on September 14 for students applying for admission.
Admissions Offices and the ITS Helpdesk are attending training for resetting passwords and answering authentication/security questions.
Financial Aid will go live the first week in October to begin awarding Freshman Scholarships. The final stages of testing are in progress, security is being finalized, and queries will be moved to the production environment.
Student Financials is testing and building internal modules, including tuition/fee calculation, refunds, billing and the late fee process.
Student Records is converting catalog and schedule data and Career Program Plans.
The MyBlue Portal will go live on September 14 for students applying for admission.
Admissions Offices and the ITS Helpdesk are attending training for resetting passwords and answering authentication/security questions.
Financial Aid will go live the first week in October to begin awarding Freshman Scholarships. The final stages of testing are in progress, security is being finalized, and queries will be moved to the production environment.
Student Financials is testing and building internal modules, including tuition/fee calculation, refunds, billing and the late fee process.
Student Records is converting catalog and schedule data and Career Program Plans.
Tuesday, August 18, 2009
PeopleSoft Project News - August 17, 2009
Testing of the online admissions application continues along with other tasks in preparation for a September 14 Admissions go live date.
Image Now testing continues for Graduate Admissions.
Student Records is looking for lost data. It was in PeopleSoft one day and it was gone the next. (Watch next week's blog entry for possible answers to the "lost data mystery.")
Image Now testing continues for Graduate Admissions.
Student Records is looking for lost data. It was in PeopleSoft one day and it was gone the next. (Watch next week's blog entry for possible answers to the "lost data mystery.")
Tuesday, August 11, 2009
PeopleSoft Project News - August 10, 2009
Admissions will be testing the PeopleSoft Campus Solutions links in the MyBlue portal to prepare for the first go-live on September 14.
A final planning meeting for the conversion of biographical/demographic data is scheduled for Monday, August 10. The go-live date is August 18.
WebFocus training is offered again this week in Lincoln. Two UNK staff are attending, so five people will be as up-to-speed as possible with this new tool.
As of Monday, August 10, the CedarCrestone consultants have transitioned end-user support for application security issues to the Campus Security Coordinators. For UNK, that’s Mitch O’Neill.
A final planning meeting for the conversion of biographical/demographic data is scheduled for Monday, August 10. The go-live date is August 18.
WebFocus training is offered again this week in Lincoln. Two UNK staff are attending, so five people will be as up-to-speed as possible with this new tool.
As of Monday, August 10, the CedarCrestone consultants have transitioned end-user support for application security issues to the Campus Security Coordinators. For UNK, that’s Mitch O’Neill.
Tuesday, August 4, 2009
PeopleSoft Project News - August 3, 2009
Testing of the online application process by Admissions was derailed last week by issues related to the assignment of the internal identifier called nu-id. They’ll try again this week.
Tim and Janet from Residential and Greek Life are spending Monday and Tuesday with a StarRez consultant. Software is installed on the servers and on some workstations in a training lab. Student Accounts is participating and ITS will be looking at data conversion and interfaces to PeopleSoft.
Graduate Admissions is spending several days with an Image Now consultant working on a pilot document imaging and workflow project.
Three ITS staff members are in Lincoln this week attending WebFocus training.
Tim and Janet from Residential and Greek Life are spending Monday and Tuesday with a StarRez consultant. Software is installed on the servers and on some workstations in a training lab. Student Accounts is participating and ITS will be looking at data conversion and interfaces to PeopleSoft.
Graduate Admissions is spending several days with an Image Now consultant working on a pilot document imaging and workflow project.
Three ITS staff members are in Lincoln this week attending WebFocus training.
Tuesday, July 28, 2009
PeopleSoft Project News - July 27, 2009
Admissions has two additional tasks on their to-do list this week. They have one week to complete their security definitions and they must brief the ITS Helpdesk on possible on-line application for admission issues to they can prepare to answer questions from applicants.
Large scale testing took place for the bio/demo conversion data. This involved the entire project team.
Rory Weaver, the Project Manager, will be in Kearney on Wednesday, July 29, to provide a status update to the Administrative Council and administrative directors.
Large scale testing took place for the bio/demo conversion data. This involved the entire project team.
Rory Weaver, the Project Manager, will be in Kearney on Wednesday, July 29, to provide a status update to the Administrative Council and administrative directors.
Tuesday, July 21, 2009
PeopleSoft Project News - July 20, 2009
Admissions no longer has to debate the merits of converting data prior to their go-live date in October. The Project Manager says there is not enough time and their conversion must take place at a later date.
Hardware will be installed this week so that servers will be available for StarRez, the housing software, and Image Now, the document imaging application, and so that storage for those applications and others is readily available. Both StarRez and Image Now will utilize virtualized hardware under VMware.
Hardware will be installed this week so that servers will be available for StarRez, the housing software, and Image Now, the document imaging application, and so that storage for those applications and others is readily available. Both StarRez and Image Now will utilize virtualized hardware under VMware.
Tuesday, July 14, 2009
PeopleSoft Project News - July 13, 2009
Admissions is debating the importance of converting applications from the current Plus system to PeopleSoft before their Fall, 2009, go live date. Processes could be more efficient with all of the data in one place, namely PeopleSoft, but time is running short, so alternatives are under review. The applications could be converted later rather than sooner.
ITS has scheduled a hardware installation for the week of July 20. As soon as new hardware is in place, both StarRez, the housing application, and Image Now, the document imaging system, will be installed. StarRez and Image Now consultants will be on site in Kearney during the week of August 3.
Training for WebFocus, the reporting tool selected for the PeopleSoft project, is also scheduled for the week of August 3.
There is no Portal news this week. Paul Swenson, our UNK Portal guy, is out of the office for three weeks of National Guard training/duty. We look forward to his return—and he’s only been gone a week!
ITS has scheduled a hardware installation for the week of July 20. As soon as new hardware is in place, both StarRez, the housing application, and Image Now, the document imaging system, will be installed. StarRez and Image Now consultants will be on site in Kearney during the week of August 3.
Training for WebFocus, the reporting tool selected for the PeopleSoft project, is also scheduled for the week of August 3.
There is no Portal news this week. Paul Swenson, our UNK Portal guy, is out of the office for three weeks of National Guard training/duty. We look forward to his return—and he’s only been gone a week!
Monday, July 6, 2009
PeopleSoft Project News - July 6, 2009
The Undergraduate Admissions Office is working on configuration of the online admissions application.
The Campus Portal is called MyBLUE. A branding scheme for MyBLUE has been completed. The design has been approved and implemented in a development environment. Completion of this task will ensure that when MyBLUE goes live for applicants in September it will have the UNK look.
For StarRez, the housing software, residence hall and room data is being compiled and an on-campus visit for set-up and training will be scheduled in late July or early August. The hardware should be installed by July 24.
The Campus Portal is called MyBLUE. A branding scheme for MyBLUE has been completed. The design has been approved and implemented in a development environment. Completion of this task will ensure that when MyBLUE goes live for applicants in September it will have the UNK look.
For StarRez, the housing software, residence hall and room data is being compiled and an on-campus visit for set-up and training will be scheduled in late July or early August. The hardware should be installed by July 24.
Subscribe to: